Shri Maneesh Kumar Shrivastav, ED (Engineering) NTPC Ltd. chaired the pre-bid discussion on the construction of stage II of NTPC Lara on 21st December 2022 in the presence of Shri Diwakar Kaushik, ED (Lara). Representatives of BHEL and L&T participated in this discussion to clarify their doubts on various issues related to the construction of Lara stage-II. It is to mention that the present Lara plant is going for capacity addition with another 1600 MW with the construction of 02 more units of 800 MW each.
On this occasion, Shri Shrivastav also visited the central control room, model room, simulator, Boiler, Turbine and Stage-II site.